Rhinelander Streetscape Project Will End In October

WXPR

Mother Nature has thrown a problem or several into the works, but a Rhinelander official says the downtown construction project known as "Streetscape" is likely to be finished for this year in October.

The Davenport Street bridge has reopened and City Administrator Kristina Aschenbrenner says this year's work should be done this fall...

"....the schedule that we had had us finishing in the first week of October. We've had a couple of delays, so our overall schedule is maybe a week behind, but we had anticipated maybe a few weeks of cushion in there so we will get this project done by the end of October...."

She says the weather and some late deliveries have slowed the overall progress of the $9 million dollar downtown reconstruction. More information is here.